Unit 12 The Western Centre, Bracknell
Client:
Britel Fund Trustees

Contract Administrator:
Workman LLP

Programme:
17 Weeks

Value:
£532,000


Please click to
download a
PDF version

Description:

Open Contracts were appointed to convert one large warehouse unit into 3 separate units on this industrial site in Bracknell, Berks.

Scope:

Works included the demolition of the offices whilst retaining some of the features for re use in the newly created spaces. The warehouse was sub divided by large steel beams, blockwork and stud walls to create 3 smaller industrial units. New services and facilities were provided to each unit. External works included new sectional doors, pedestrian shop fronts and cladding to the front elevation. The roof was also repaired.

For further information on this project, please contact Peter Smith (Director) on 0207 240 7711